The first 50.4 MW tranche is commissioned, with first power flow on 22 September 2026. Viviid is delivering end-to-end Balance of System works for the 630 MW wind project.
Through competitive bidding, Viviid secured the Balance of System (BoS) contract for NTPC Renewable Energy Limited’s 630 MW wind project in Jamnagar, Gujarat.
Our scope extends from micro-siting and land acquisition to civil works, the 33 kV network, pooling substations and the 220 kV EHV line connecting to the CTUIL substation. It includes permits and approvals from authorities such as AAI, MOD, GEDA and CEIG, project commissioning and three years of operation and maintenance.
Owner: NTPC Renewable Energy Limited Location: Jamnagar, Gujarat Overall status: Under execution; first tranche of 50.4 MW commissioned
Commissioning milestones
Project status as of this commissioning update
50.4 MW commissioned. First power flow achieved on 22 September 2026.
PSS-2 commissioned. Capacity to evacuate 315 MW.
220 kV double-circuit EHV line commissioned. The line connects PSS-2.
PSS-1 commissioning in progress with its associated EHV line.
Our scope of work
Micro-siting, surveys and studies
Micro-siting of 200 wind turbine locations, land surveys and power evacuation studies.
Land acquisition and approvals
Land acquisition for 200 wind turbine locations, tied up with access, together with land permits and all statutory approvals.
Civil works
Internal and external pathways for machinery movement, wind turbine platforms and crane pad works.
33 kV electrical network
Design, supply, erection and civil works, including load flow studies and optimized loss calculations.
Pooling substations
Two 33/220 kV pooling substations, rated at 315 MVA each, including transformers, Static Var Generators (SVGs) and harmonic filters.
220 kV EHV line
55 km of 220 kV transmission line connecting the pooling substations to CTUIL Jamkhambalia Grid Substation.
Logistics and right-of-way
Logistics enablement, removal of encroachments, line heightening and right-of-way agreements.
Commissioning
Project commissioning with all statutory approvals.